Ohio River Bridge Progress - June 2006

The bridge is presently about 85% complete, with the current anticipated completion date being November 30, 2007. The Ohio deck is complete and we are getting ready to place the parapets and median barrier. All of the steel is placed on the arch and the cable hangers should be completed by the last part of June 2007. After completing the cable hangers, the remaining falsework will be removed from the arch structure. The first deck placement has been made on the WV approach to the arch, and placement of reinforcing steel and stay in place metal forms continues.

 

Click thumbnail to see larger image.

Installing cables at the Tie Girder Anchorage.
Installing cables at the Tie Girder Anchorage.

Installing stay in place metal deck forms on the WV approach.
Installing stay in place metal deck forms on the WV approach.

Installing stay in place metal deck forms on the WV approach.
Installing stay in place metal deck forms on the WV approach.

Installing reinforcing steel bars in the WV approach deck.
Installing reinforcing steel bars in the WV approach deck.

Installing reinforcing steel bars in the WV approach deck.
Installing reinforcing steel bars in the WV approach deck.

Installing rebar in the deck & median barrier & setting up the deck finish machine.
Installing rebar in the deck & median barrier & setting up the deck finish machine.

Construction on the outside overhang forms for the deck.
Construction on the outside overhang forms for the deck.

Setting up the Bidwell deck finishing machine.
Setting up the Bidwell deck finishing machine.

Cable hangers in place, looking toward WV from the Arch.
Cable hangers in place, looking toward WV from the Arch.

Top of the upstream arch rib.
Top of the upstream arch rib.

Installing the 27 individual strands per hanger in the tie girder anchorage.
Installing the 27 individual strands per hanger in the tie girder anchorage.

Stay in place deck froms and rebar placement progress on the WV approach deck.
Stay in place deck froms and rebar placement progress on the WV approach deck.

Cable anchorage in the arch rib.
Cable anchorage in the arch rib.

Installing cables into the arch rib anchorage.
Installing cables into the arch rib anchorage.

Installing cables into the tie girder anchorage.
Installing cables into the tie girder anchorage.

Stay in place deck froms and rebar placement progress on the WV approach deck
The WV approach deck from the top of the arch.

Aerial photo of the bridge.
Aerial photo of the bridge.

Aerial photo of the bridge.
Aerial photo of the bridge.

Connecting the last section of structural steel, over Rte. 892, at Abutment 2.
Connecting the last section of structural steel, over Rte. 892, at Abutment 2.

Arch rib anchorage assembly.
Arch rib anchorage assembly.

 

Aerial photo of the bridge.
Aerial photo of the bridge.

Aerial photo of the bridge.
Aerial photo of the bridge.

 

 

   
Home | Project Info | Interchange Designs | Photos | Press | Contact | Top of Page

This website provided as a public service by the West Virginia Division of Highways.
For more information about the Appalachian Corridor D Project, or to comment on this website,
please contact the WVDOH by email feedback@wvcorridord.com or use our Comment Form.
Please note: This website is presented for informational purposes only.
Schedules, maps, dates, narrative descriptions, and other content provided are subject to change.