Ohio River Bridge Progress - July 2006

Construction has progressed significantly on the Ohio River Bridge portion of the Corridor D project which will link West Virginia and Ohio. Bridge construction is already 43% complete and remains on target for a
September 2007 opening.

All of the coffer dams for the river piers are in place. 20 of 22 pier columns are completed and 6 of 11 piers are completely finished. The West Virginia access road is completed for construction and future maintenance. Work is nearly completed on the Ohio abutment. Erection of the arch structural steel has begun across the main channel of the Ohio River and should be completed by the end of the year. Erection of the structural steel for the West Virginia approach is expected to begin in the next few weeks. The structural steel will support the roadway or driving surface.

Click thumbnail to see larger image.
Beginning of the arch structural steel (Ohio side). Beginning of the arch structural steel (Ohio side). Beginning of the arch structural steel (Ohio side). Beginning of the arch structural steel (Ohio side).

Beginning of the arch structural steel (Ohio side).

Bridge alignment looking west from WV Rt. 892 (DuPont Road) across the Ohio River.
Bridge alignment looking west from WV Rt. 892 (DuPont Road)
across the Ohio River.

Bridge alignment from top of DuPont Hill (WV Rt. 892).
Bridge alignment from top of DuPont Hill (WV Rt. 892).

Looking east from Ohio side at piers on Blennerhassett Island.
Looking east from Ohio side at piers on Blennerhassett Island.

Ohio abutment with wooden pier form in foreground.
Ohio abutment with pier form in foreground.




February 2006

Click thumbnail to see larger image.

Bridge alignment looking west from Rt. 892 (Dupont Road) across the Ohio River.
Bridge alignment looking west from Rt. 892 (Dupont Road) across the Ohio River.

Footing for bridge pier - WV side.
Footing for bridge pier - WV side.

Steel reinforcement for concrete pier - Ohio side.
Steel reinforcement for concrete pier - Ohio side.

Bridge construction from Ohio Rt. 7.
Bridge construction from Ohio Rt. 7.

Looking east from Ohio side at piers on Blennerhassett Island.
Looking east from Ohio side at piers on Blennerhassett Island.

Crane and pier construction - Ohio side.
Crane and pier construction - Ohio side.

Casing for drilled piling, into bedrock 100 ft. down - Ohio side.
Casing for drilled piling, into bedrock 100 ft. down - Ohio side.

Bridge alignment from top of Dupont Hill (WV Rt. 892).
Bridge alignment from top of Dupont Hill
(WV Rt. 892).

 

 

   
Home | Project Info | Interchange Designs | Photos | Press | Contact | Top of Page

This website provided as a public service by the West Virginia Division of Highways.
For more information about the Appalachian Corridor D Project, or to comment on this website,
please contact the WVDOH by email feedback@wvcorridord.com or use our Comment Form.
Please note: This website is presented for informational purposes only.
Schedules, maps, dates, narrative descriptions, and other content provided are subject to change.