Appalachian Corridor D. Project Information
West Virginia Department of Transportation
Black Bar Project Info Interchange Designs Photos Press Contact



Direct comments & questions here.


slideshow


Blennerhassett Bridge webcam.

Click here for live Blennerhassett Bridge updates.

 

Bridge Set for Spring Opening

11/15/2007

The Blennerhassett Bridge should be open by late April or early May, finishing the last piece of the Corridor D project, said officials with the West Virginia Department of Transportation.

WVDOT officials, along with representatives from the Ohio Department of Transportation, met with media Wednesday at the bridge to give a status report on the project and announce when it was expected to be completed.

The 4,009-foot Blennerhassett Bridge, which spans the Ohio River and Blennerhassett Island, is the last major component of the Corridor D project left to be completed, said State Highway Engineer Marvin Murphy.

‘‘We are about 97 percent completed,’’ Murphy said.

The Corridor D project is a multilane highway extending from the Ohio State line at Parkersburg to I-79 at Clarksburg. It was designated as part of the Appalachian Development Highway System by the Appalachian Regional Development Act of 1965 and later designated as part of the National Highway System by the NHS Act.

‘‘We are about 40 years into getting the last piece of Corridor D in place,’’ Murphy said. ‘‘It is the largest project West Virginia has let in one total contract costing around $120 million.

‘‘It has been a very good project. It has been one that has had good cooperation among all sources. The struggle to get this bridge across the river was not easy.’’

At one time, it was believed the bridge would have been completed by the end of August 2007. Then the completion date was moved to the end of November.

‘‘We had a very aggressive schedule from the beginning,’’ Murphy said. ‘‘We had made some changes to the design on the deck, which has delayed us a little further along in the project.

‘‘Those were necessary changes we were more comfortable with making at this time during construction. Right now, we are at the point where our delays will force us into the upcoming spring, mainly because of the weather.’’

The majority of the work that still needs to be done includes putting down the latex modified concrete overlay on the bridge deck, which needs a certain amount of warmth.

‘‘Right now, that will require 50 degree days to do,’’ Murphy said. ‘‘We are running short on those days.’’

Officials estimated crews would need at least seven weeks to finish putting the overlay in.

‘‘The other thing we have to do is the stressing of the arch cables themselves,’’ Murphy said.

The cables on the bridge are tightened to continuously support the load required of them.

‘‘That has to be done in a certain sequence,’’ Murphy said. ‘‘That is suppose to be done after the overlay is in place and has cured.’’

Officials estimate the tightening of the cables will take around six weeks to complete.

Other work will have to be done in restoring Blennerhassett Island, including top soil placement, tree replacement and the placing of bird boxes, which is expected to take five weeks.

Also, officials estimated four more weeks of earthwork along some of the approaches, two weeks for the road striping and eight weeks of electrical work putting in lighting and more.

‘‘We want to make sure it is done right,’’ Murphy said. ‘‘We will take that time to make sure it was done right.’’

Construction of the new bridge and its approaches has being handled by Walsh Construction and a crew of around 220.

Officials from around the area have said the completion of Corridor D will open up new areas of development. With access the road provide, the road will help cut down on heavy trucks continually rolling through the city streets of Belpre and Parkersburg.

Rusty Roten, district manager for WVDOT District 3, said the bridge was coming along nicely and will be a major benefit to the area.

‘‘The bridge is looking really good,’’ he said. ‘‘I like to see something real rather than just artists’ renderings.

‘‘It is nice to look out here and see something.’’

With the exception of a few minor odds and ends, the Ohio side approaches are ready to open, said Steve Williams, construction engineer for ODOT District 10.

The $22 million portion of the project handled by ODOT includes five small roadway bridges and the approches to the main bridge outside Belpre.

‘‘We are substancially complete,’’ Williams said. ‘‘Our end of the project can be opened at any time.

Posted with permission from The Parkersburg News & Sentinel

Back to Press

 

   
Home | Project Info | Interchange Designs | Photos | Press | Contact | Top of Page

This website provided as a public service by the West Virginia Division of Highways.
For more information about the Appalachian Corridor D Project, or to comment on this website,
please contact the WVDOH by email feedback@wvcorridord.com or use our Comment Form.
Please note: This website is presented for informational purposes only.
Schedules, maps, dates, narrative descriptions, and other content provided are subject to change.